Treatment

The Town appropriated $10.4 million on June 20, 2017 for the construction of a water treatment plant and associated piping.  Substaintial completion of the project is expected in January 2019 which will be followed by several weeks of testing.  We're planning on using the plant to produce water by the end of February 2019.  Progress updates will be posted on a regular basis.

March Update: The plant is now fully operational and has been treating all of the Town's water since March 6th.  It will take several cycles of hydrant flushing to clear out the sediment in the water mains but manganese is no longer being pumped into the distribution system.

Raw water transmission mains will be installed along North Street (Boardman Lane to Ipswich Road), Ipswich Road (North Street to Averill Street), Averill Street, Perkins Row (Stone Bridge to Meetinghouse Lane), Meetinghouse Lane and Howlett Street (Meetinghouse Lane to Route 1) as part of the water treatment plant project.

June 28th Update: The only remaining portion of the project is the final paving of the trench on Route 1 near Averill Street.

Below are some common questions about Topsfield's water treatment processes and the water treatment plant project.  Please call the Water Department if you have any additional questions or would like more information.

1. How is our water currently treated?

Topsfield's water receives the following treatment before entering the distriubtion system:

  • Disinfection - Sodium Hypochlorite is added to disinfect the water.
  • Fluoridation - Sodium Fluoride is added to prevent tooth decay.
  • pH Adjustment - Potassium Hydroxide is added to reduce Lead and Copper corrosion rates.
  • Sequestration - An ortho/poly-phosphate blend is added to the water to delay the creation of nuiscnace manganese particles.

These treatment processes are done through 'inline' treatment.  The chemicals are added to the water by a positive displacement pump as the water leaves the source water facility.  Some reactions take place quickly such as pH adjustment and fluoridation but others such as disinfection take some time to run to completion.  Inline treatment does not remove any constituents from the water, we are only able to add things to the water.

 

Water Treatment Plant Information

The project is nearly complete and the plant is fully operational.  All that remains are punch list items such as loaming and seeding.  The plant started full operations on March 6, 2019.

Spring Hydrant Flushing

Flushing is scheduled to start on April 8th.  Click here to view the schedule.

Pay your water bill online

81009 83017 0Please visit the Unibank site to pay your water or tax bills online.

 
 

Water Department

279 Boston Street

Topsfield, MA 01983

978.887.1517

978.887.1543 (Fax)

911 -  After Hours Emergency

Hours: Monday-Friday 7 AM to 3:30 PM

Highway Department

279 Boston Street

Topsfield, MA 01983

978.887.1542

978.887.1543 (Fax)

Hours: Monday-Friday 7 AM to 3 PM